Building Regulations Part P: Non-HRB Domestic Compliance Guide for Small Practices

Approved Document P — Electrical Safety (Dwellings) · Building Safety Act 2022 · Non-HRB projects

Summary

What the Building Safety Act requires for Part P on non-HRB domestic jobs

Part P applies to electrical installations in dwellings, including gardens and shared amenities. Every extension and refurbishment includes notifiable electrical work — new circuits for kitchens, showers or EV chargers, consumer unit changes, additions in bath/shower rooms — and the compliance route is binary: a registered competent person (NICEIC, NAPIT, etc.) self-certifies and notifies, or the work goes through Building Control with inspection and testing.

The Principal Designer (BSA) does not design the electrics on most domestic jobs, but the coordination duty still applies: is someone competent designing the installation (not just installing it), does the consumer unit have capacity for the added load (electric showers, heat pumps and EV chargers stack up fast), and will certification actually be delivered? Writing the certification deliverables into the specification is the cheapest compliance instrument available.

Since consumer units must now have non-combustible enclosures and new circuits typically need RCD protection (and increasingly arc fault consideration under BS 7671 Amendment 2), a 'like-for-like' attitude to older installations is a false economy the client should be advised out of, in writing.

Key design risks and evidence needed (RIBA Stages 2–4)

Standards and references you should be citing

Notifiable vs non-notifiable domestic electrical work

WorkNotifiable?Evidence to log
New circuit (kitchen, shower, EV charger)YesEIC + scheme notification or BC approval
Consumer unit replacementYesEIC + scheme notification
New/altered work in bathroom zonesYesEIC + scheme notification
Adding sockets/lights to existing circuit (outside special locations)NoMinor works certificate still expected
Like-for-like accessory replacementNoNone, but note in project record

Common pitfalls that catch out sole practitioners

Frequently asked questions

What electrical certification should I collect at handover on a domestic job?

An Electrical Installation Certificate (or Minor Works Certificates for small additions) with schedules of inspection and test results to BS 7671, plus the competent person scheme notification confirmation (or Building Control acceptance where that route was used). As PD, store them in the health and safety file / handover pack.

Is replacing a consumer unit notifiable under Part P?

Yes. A consumer unit replacement is notifiable building work, must be certified to BS 7671, and modern units must have non-combustible enclosures. It is one of the most commonly skipped notifications in domestic refurbishment — check for the paperwork.

Track this natively instead of in Word templates

PD Pathway gives small practices an automated Parts A–T relevant-requirements tracker, stage-by-stage Principal Designer checklists and one-click compliance documents — built strictly for non-HRB projects. First project free, then from £10 per project or £99/yr unlimited.