Building Regulations Part R: Non-HRB Domestic Compliance Guide for Small Practices

Approved Document R — Infrastructure for Electronic Communications · Building Safety Act 2022 · Non-HRB projects

Summary

What the Building Safety Act requires for Part R on non-HRB jobs

Part R Volume 1 (new dwellings) requires gigabit-ready physical infrastructure — ducting from the plot boundary to a suitable termination point in the dwelling — and a gigabit-capable connection where one can be secured within the £2,000 per-dwelling cost cap. If not, the requirement steps down to the next best available (superfast, then standard) while still installing the gigabit-ready ducting.

Volume 2 applies R1 to buildings other than new dwellings undergoing major renovation: in-building physical infrastructure so occupants can be connected, with common access points for multi-occupancy buildings. Most domestic extension work is out of scope, but flat conversions and mixed-use refurbishments are frequently in it.

As Principal Designer (BSA) the duty is evidential: AD R expects the connectivity steps to be documented — operator enquiries, quotes, the option selected — and Building Control can ask for that documentation at completion. It is the least technical Approved Document and the most purely administrative; a tidy tracker entry with three attachments discharges it.

Key design risks and evidence needed (RIBA Stages 2–4)

Standards and references you should be citing

Part R decision path for a new dwelling

StepQuestionEvidence to log
1Is a gigabit-capable connection available within the £2,000 cap?Operator responses / quotes
2If not — is a superfast (≥30 Mbps) connection available?Availability check record
3Either way: install gigabit-ready ducting boundary-to-terminationDuct spec + as-built route drawing
4File the connectivity documentationStatement submitted with Building Control application

Common pitfalls that catch out sole practitioners

Frequently asked questions

Does Part R apply to a house extension?

No. Volume 1 applies to new dwellings (including conversions creating dwellings) and Volume 2's R1 applies to major renovation of buildings containing dwellings or workplaces. A straightforward domestic extension engages neither — record 'not applicable' with the reasoning in your tracker.

What if no gigabit network operator serves the site?

The requirement steps down: if a gigabit-capable connection cannot be secured within the £2,000 cost cap, provide the next best available connection, and in all cases install gigabit-ready physical infrastructure (ducting to a termination point) so the dwelling can be connected later without civils. Keep the operator correspondence as evidence.

Track this natively instead of in Word templates

PD Pathway gives small practices an automated Parts A–T relevant-requirements tracker, stage-by-stage Principal Designer checklists and one-click compliance documents — built strictly for non-HRB projects. First project free, then from £10 per project or £99/yr unlimited.